Primary Treatment

Primary clarifiers remove settleable solids and grease before biological treatment, reducing the load on the aeration basin.

Primary clarifierA primary clarifier settles raw solids and floats grease. Primary sludge is pumped from the floor.Scum and grease skimmedAbout 2 hours detentionremoves 50 to 65% of TSS and 25 to 35% of BODPrimary sludge
Primary clarifier: settleable solids form primary sludge, floating material is skimmed, and primary effluent flows to aeration.

What primaries remove

Typical primary clarifiers remove about 50 to 70% of TSS and 25 to 40% of BOD. White River's design removals are 60% TSS and 32% BOD. White River's design primary effluent is BOD 150 mg/L and TSS 96 mg/L from influent BOD 220 and TSS 240.

Key numbers

  • Detention time: often 1.5 to 2.5 hours. White River: four 65 ft clarifiers with 893,554 gal total volume; at 8.0 MGD, detention is about 2.7 hours.
  • SOR: design values are often 800 to 1,200 gpd/ft² at average flow. White River's 13,273 ft² of primary area gives about 603 gpd/ft² at 8.0 MGD.
  • Sludge concentration: anywhere from about 1 to 6% solids depending on pumping strategy and whether the primaries thicken. White River pumps about 1.2% on timers.

Effect on activated sludge

  • Less BOD and TSS to aeration means less oxygen and less sludge.
  • Grease removal reduces foam formers.
  • Too much removal can short denitrification of carbon in BNR plants.
  • Septic primary sludge (held too long) sends sulfide and odors downstream.

Good habits

  • Pump primary sludge often enough to prevent septic conditions, but not so much that it is thin.
  • Keep scum removal working.
  • Check sludge blanket and solids concentration daily.